The correct answer is that risk decreases more quickly than in traditional development. Over the course of an agile project, risk decreases rather steadily. The other responses are incorrect because until a project is finished, traditional
projects experience little decrease in risk; the achievement of business value should occur as early in the project as possible; agile projects should demonstrate visibility and adaptability from start to finish; value should show
a steady increase with increments.