The correct answer is the Gantt chart doesn’t include any information regarding the project’s cost; it is just the list of tasks Elon entered. The other responses are incorrect because a Gantt chart does provide information on the percentage
of the project completed, and which tasks have been completed; a Gantt chart gives a view of the project over time.