The correct answer is to charge nothing extra for changes if the work doesn’t increase. Typically, agile contracts can accommodate change as long as the overall volume of work doesn’t increase. The other responses are incorrect because
if the total amount of work doesn’t change, the contract doesn’t need to be renegotiated or broken; agile projects don’t need a formal change control process with the entire team’s approval.