The correct answer is incorporating refactoring into every estimate; Agile estimates should include refactoring as part of every user story. The other responses are incorrect because they are not appropriate ways for technical debt to
be handled. Technical debt should be dealt with as part of each item delivered, not after the fact or scheduled separately.