The correct answer is to hire a temp or contractor to free up Chanda. The people selected to be on an Agile team are usually, because of their knowledge level, the busiest people in an organization. However, the team itself needs members
who can most effectively help the team understand the requirements and make critical decisions. To free up Chanda’s time to devote herself to the project, it might be beneficial for the project to pay for someone (a temp or contractor)
to take over her daily responsibilities. The other responses are incorrect. The team can’t assist the stakeholder (Chanda) with her daily work, because then they’d be behind in their own work; overloading a stakeholder is contrary
to Agile principles, and would force her to make a decision on where her time is spent; Chanda’s manager is already aware of the issues.