A burnup chart tells how much work has been completed. Advantages of using a burnup chart are its ability to track project scope, items not started, or what is in progress. The other responses are incorrect because a burnup chart doesn’t
track members, work left to complete, or when the project will end. Other matrices will perform these functions.