The correct answer is that agile stakeholder management is not focused on controlling and managing; its focus is more on stewardship. The other responses are incorrect because they aren’t focuses of agile stakeholder management. There
is no implication that a stakeholder group would be smaller in an agile project, or easier to handle; agile methods don’t require that the team decides what to tell stakeholders; preferred communication is face-to-face and is never
limited to information radiators.