The imposed finish date becomes the late finish for Activity I. The late dates for each activity need to be recalculated. The dates for Activity E become______________ ES = 10 EF = 13 LS = 9LF = 12 Total float = LS - ES or 9 - 10 = (-1) or LS - EF or 12 - 13 = (-1)