Lessons learned but not documented are "lessons lost." The lessons learned knowledge database will help current project members, as well as people on future projects, make better decisions. Accordingly, the reasons for the variance, the rationale supporting the corrective action, and other related information must be documented. They require updates as part of updates to organizational process assets as an output of control costs in terms of corrective actions taken and why they were selected.