Examsnet
Unconfined exams practice
Home
Exams
Banking Entrance Exams
CUET Exam Papers
Defence Exams
Engineering Exams
Finance Entrance Exams
GATE Exam Practice
Insurance Exams
International Exams
JEE Exams
LAW Entrance Exams
MBA Entrance Exams
MCA Entrance Exams
Medical Entrance Exams
Other Entrance Exams
Police Exams
Public Service Commission (PSC)
RRB Entrance Exams
SSC Exams
State Govt Exams
Subjectwise Practice
Teacher Exams
SET Exams(State Eligibility Test)
UPSC Entrance Exams
Aptitude
Algebra and Higher Mathematics
Arithmetic
Commercial Mathematics
Data Based Mathematics
Geometry and Mensuration
Number System and Numeracy
Problem Solving
Board Exams
Andhra
Bihar
CBSE
Gujarat
Haryana
ICSE
Jammu and Kashmir
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Odisha
Tamil Nadu
Telangana
Uttar Pradesh
English
Competitive English
CBSE
CBSE Question Papers
NCERT Books
NCERT Exemplar Books
NCERT Study Notes
CBSE Study Concepts
CBSE Class 10 Solutions
CBSE Class 12 Solutions
NCERT Text Book Class 11 Solutions
NCERT Text Book Class 12 Solutions
ICSE Class 10 Papers
Certifications
Technical
Cloud Tech Certifications
Security Tech Certifications
Management
IT Infrastructure
More
About
Careers
Contact Us
Our Apps
Privacy
Test Index
PMP Certification Mix Questions Test 2
Show Para
Hide Para
Share question:
© examsnet.com
Question : 16
Total: 70
Assume that your actual costs are
$
800; your planned value is
$
1,200; and your earned value is
$
1,000. Based on these data, what can be determined regarding your schedule variance?
At +
$
200, the situation is favorable as physical progress is being accomplished ahead of your plan.
At -
$
200, the physical progress is being accomplished at a slower rate than is planned, indicating an unfavorable situation.
At +
$
400, the situation is favorable as physical progress is being accomplished at a lower cost than was forecasted.
At -
$
200, you have a behind-schedule condition, and your critical path has slipped
Validate
Solution:
Schedule variance is calculated: EV - PV or
$
1,000 -
$
1,200 = -
$
200. Because the SV is negative, physical progress is being accomplished at a slower rate than planned.
© examsnet.com
Go to Question:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
Prev Question
Next Question
More Free Exams:
ITIL 4 Foundation Practice Tests
PMP & CAPM Practice Tests
SCRUM Certification Practice Tests
Six Sigma Iassc Certification (CSSC) Practice Tests
Six Sigma Lean Certification (CSSC) Practice Tests