Much of the output from planning in other knowledge areas, such as activity cost and duration estimates, may entail risk and is reviewed during the identify risks process. This process requires an understanding of the schedule, cost, and quality management plans found in the project management plan. Estimates that are aggressive or developed with a limited amount of information are even more likely to entail risk and, therefore, must also be an input to the identify risks process.