Project risk has its origin in the uncertainty that is present in all projects. Organizations and stakeholders are willing to accept varying degrees of risk, and risks that are threats to the project may be accepted if the risks are within tolerances and are in balance with the rewards to be gained. This example of adopting a fast-track schedule is a risk taken to achieve the reward created by the earlier completion date.