Examsnet
Unconfined exams practice
Home
Exams
Banking Entrance Exams
CUET Exam Papers
Defence Exams
Engineering Exams
Finance Entrance Exams
GATE Exam Practice
Insurance Exams
International Exams
JEE Exams
LAW Entrance Exams
MBA Entrance Exams
MCA Entrance Exams
Medical Entrance Exams
Other Entrance Exams
Police Exams
Public Service Commission (PSC)
RRB Entrance Exams
SSC Exams
State Govt Exams
Subjectwise Practice
Teacher Exams
SET Exams(State Eligibility Test)
UPSC Entrance Exams
Aptitude
Algebra and Higher Mathematics
Arithmetic
Commercial Mathematics
Data Based Mathematics
Geometry and Mensuration
Number System and Numeracy
Problem Solving
Board Exams
Andhra
Bihar
CBSE
Gujarat
Haryana
ICSE
Jammu and Kashmir
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Odisha
Tamil Nadu
Telangana
Uttar Pradesh
English
Competitive English
Certifications
Technical
Cloud Tech Certifications
Security Tech Certifications
Management
IT Infrastructure
More
About
Careers
Contact Us
Our Apps
Privacy
Test Index
PMP Certification Monitoring and Controlling Test 3
Show Para
Hide Para
Share question:
© examsnet.com
Question : 42
Total: 70
Halfway through a project, the project manager determines that the project is behind schedule. The project manager reviews the issue log and notices that reviews, which are mandatory for the project to move forward, have taken longer than expected and have affected the critical path. Project delays will negatively impact stakeholder engagement.
What should the project manager do to communicate the schedule delays to the project sponsor?
Inform the project sponsor that the project is on schedule and ask the team to deliver tasks faster to compensate for any review delays.
Revise the schedule to detach the reviews from the critical path, and report that the project is on schedule.
Report the actual schedule status to all stakeholders and modify the stakeholder engagement plan to reduce the engagement baseline.
Report the actual schedule status to the project sponsor, and follow the stakeholder engagement plan to expedite future reviews.
Validate
Solution:
© examsnet.com
Go to Question:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
Prev Question
Next Question