Examsnet
Unconfined exams practice
Home
Exams
Banking Entrance Exams
CUET Exam Papers
Defence Exams
Engineering Exams
Finance Entrance Exams
GATE Exam Practice
Insurance Exams
International Exams
JEE Exams
LAW Entrance Exams
MBA Entrance Exams
MCA Entrance Exams
Medical Entrance Exams
Other Entrance Exams
Police Exams
Public Service Commission (PSC)
RRB Entrance Exams
SSC Exams
State Govt Exams
Subjectwise Practice
Teacher Exams
SET Exams(State Eligibility Test)
UPSC Entrance Exams
Aptitude
Algebra and Higher Mathematics
Arithmetic
Commercial Mathematics
Data Based Mathematics
Geometry and Mensuration
Number System and Numeracy
Problem Solving
Board Exams
Andhra
Bihar
CBSE
Gujarat
Haryana
ICSE
Jammu and Kashmir
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Odisha
Tamil Nadu
Telangana
Uttar Pradesh
English
Competitive English
CBSE
CBSE Question Papers
NCERT Books
NCERT Exemplar Books
NCERT Study Notes
CBSE Study Concepts
CBSE Class 10 Solutions
CBSE Class 12 Solutions
NCERT Text Book Class 11 Solutions
NCERT Text Book Class 12 Solutions
ICSE Class 10 Papers
Certifications
Technical
Cloud Tech Certifications
Security Tech Certifications
Management
IT Infrastructure
More
About
Careers
Contact Us
Our Apps
Privacy
Test Index
PMP Certification Planning Questions Test 4
Show Para
Hide Para
Share question:
© examsnet.com
Question : 9
Total: 45
The research and development (R&D) team has been working on developing a new software product for nine months and feel the product is now ready for release to the market and for final handover to the operations team. The operations manager asks the operations team to do a quick test and report the findings. The report highlights that there are many changes to this new product's interface of which the operations team was not aware. This will require new training.
What should the project manager have done?
Understood that the R&D and operations teams are two different entities and established a separate transfer project.
Met with the operations manager and given the entire operations team a walk-through of the product beforehand.
Included operations resources in the project to ensure knowledge transfer between the project and operations for implementation.
Held two days of training to detail the changes and make the operations team comfortable with the changes.
Validate
Solution:
© examsnet.com
Go to Question:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
Prev Question
Next Question
Similar Free Exams:
ITIL 4 Foundation Practice Tests
PMP & CAPM Practice Tests
SCRUM Certification Practice Tests
Six Sigma Iassc Certification (CSSC) Practice Tests
Six Sigma Lean Certification (CSSC) Practice Tests