Because the Staffing Management Plan does determine the release criteria for project team members. 1 is incorrect because this is a false statement. 2 is incorrect because this term is not valid. 3 is incorrect because the Staffing Management Plan is the best choice as it is the most specific answer. The staffing management plan is a subset of the HR management plan.