In this situation, the Project Manager has no information on the timing, anticipated frequency, or impact of the expected rough weather. Option D may not be possible as there is not enough information. The best option is to accept the risk but plan a contingency reserve in terms of cost and time in case the risk occurs. Option A and B are passive approaches and are not recommended for a good Project Manager who should always be proactive in his approach toward risk management.