As seen in the question, the project is on track and on schedule, so there is no problem as far as project performance is concerned. There should have been a better emphasis on Planning the project so that the right scope and requirements could have been developed. This would have resulted in the correct deliverables being produced which would have been according to the requirements of the stakeholders.