Answer (c) Cost Variance = Earned Value (EV) - Actual Cost (AC). Positive cost variance indicates that the project is under budget. Similarly, Schedule Variance = Earned Value (EV) - Planned Value (PV). Positive schedule variance indicates that the project is ahead of schedule.