The Sprint Backlog is created during the Sprint Planning and includes the items selected from the
Product Backlog (by the Development Team) and the tasks created by decomposing the items (by the
Development Team).Developers keep adding tasks during the Sprint, so the Sprint Backlog updates.
It's the Development Team's plan for the current Sprint. This plan is not detailed upfront.If the
Development Team cannot deliver some of the items, they will go back to the Product Backlog and will
be ordered again; they do not go to the next Sprint automatically.Each task is assigned to one
developer or a pair of developers but the ownership is still shared. Items are not assigned or owned
by specific developers, all of them share accountability.