The Product Owner is responsible to make all items clear and understood. If the problem wasn't
solved, then there's no option other than leaving it to go back to the Product Backlog at the end of
the Sprint and be done later. The team is cross-functional and doesn't use external help. We don't
deliver partially complete items; everything should be done based on the definition of "Done".