Examsnet
Unconfined exams practice
Home
Exams
Banking Entrance Exams
CUET Exam Papers
Defence Exams
Engineering Exams
Finance Entrance Exams
GATE Exam Practice
Insurance Exams
International Exams
JEE Exams
LAW Entrance Exams
MBA Entrance Exams
MCA Entrance Exams
Medical Entrance Exams
Other Entrance Exams
Police Exams
Public Service Commission (PSC)
RRB Entrance Exams
SSC Exams
State Govt Exams
Subjectwise Practice
Teacher Exams
SET Exams(State Eligibility Test)
UPSC Entrance Exams
Aptitude
Algebra and Higher Mathematics
Arithmetic
Commercial Mathematics
Data Based Mathematics
Geometry and Mensuration
Number System and Numeracy
Problem Solving
Board Exams
Andhra
Bihar
CBSE
Gujarat
Haryana
ICSE
Jammu and Kashmir
Karnataka
Kerala
Madhya Pradesh
Maharashtra
Odisha
Tamil Nadu
Telangana
Uttar Pradesh
English
Competitive English
Certifications
Technical
Cloud Tech Certifications
Security Tech Certifications
Management
IT Infrastructure
More
About
Careers
Contact Us
Our Apps
Privacy
Test Index
Scrum Master Certification Practice Test 4
Show Para
Hide Para
Share question:
© examsnet.com
Question : 13
Total: 50
Part of the team's Definition of "Done" requires creating or updating technical documentation in order to maintain the product and/or features in the future. The team's technical writer will be on vacation during the Sprint. What should you do?
Encourage the technical writers from other teams to form a specialized team to organize and plan the work for multiple teams.
The Development Team members will write it as they are still responsible for creating the documentation to make the Increment done in conformance with their Definition of "Done."
Wait until the technical writer returns before continuing with related items.
Complete all development work first while adding technical documentation to the Product Backlog to be done in a subsequent Sprint.
Validate
Solution:
All Product Backlog items selected for the Sprint are owned by the Development Team as a whole. Although individual members may work on specific tasks, the Development Team is still accountable for doing the work to deliver a shippable Increment.
© examsnet.com
Go to Question:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
Prev Question
Next Question