First of all, it's OK of the Sprint Backlog is not complete until the end of the Sprint. However,
we would try to complete it if it's possible. When the developers find out they are behind schedule
they will ask the Product Owner for help and the two roles together will adjust the work (tasks), or
reorder the times to make sure the highest value will be created at the end of the Sprint.