Sprint Planning is 8 hours for a one-month Sprint and usually shorter for
shorter Sprints. Besides the Daily Scrum always having a time-box of 15 minutes, there is no
absolute rule for time-boxes of events for Sprints of less than one month. They are only usually
shorter.