The ordering of the Product Backlog is a key mechanism for reducing and eliminating dependencies.Usually items with external dependencies are not considered “Ready” for selection unless the other team is at the Sprint Planning to make
their commitment.Development Teams should deliver an Increment of product functionality every Sprint.