Let 1 worker does 1 unit work in a day.
Let 150 workers can finish the work in (n - 8 ) days, if all workers work all the days.
Then, total work = 150(n - 8) -------(i)
Also, 150 workers work on day 1, 146 workers work on day 2, ... and so on. Work is completed in n days.
Thus, total work = 150 + 146 +....(n terms)
This is an arithmetic progression with first term,a = 150, d = - 4.
Thus, total work =
[2a+(n−1)d] =
[2(150)+(n−1)(−4)] =
[300−4n+4]=
[304−4n]=n(152−2n) ----(ii)
Comparing equations (i) and (ii),
⇒
150(n−8)=n(152−2n)⇒
75(n−8)=n(76−n)⇒
75n−600=76n−n2⇒
n2−n−600=0⇒
(n−25)(n+24)=0⇒
n=25,−24∵ n cannot be negative , ⇒ n = 25
⇒ Number of days in which the work was completed = 25