A = 10 days ⇒ A + B = 20/3 days ⇒ A + B + C = 40/7 days L.C.M. of 10, 20/3 and 40/7 is 40 (total work). ⇒ Efficiency of A = 40 ÷ 10 = 4 ---- (1) ⇒ Efficiency of A + B = 40 ÷ 20/3 = 6 ⇒ Efficiency of A + B + C = 40 ÷ 40/7 = 7 ---- (2) From (2) – (1) ⇒ Efficiency of B + C = 7 – 4 = 3 ⇒ B and C together do the same piece of work = 40/3 days ∴ B and C together do the same piece of work in 40/3 days.