Scope validation leads to project acceptance. 1 is incorrect because it is not an optional process. 2 is incorrect because it may be mandatory, but this isn’t the reason why scope validation should occur. 3 is incorrect because scope validation should happen with all projects regardless of the organization’s requirements to do so.