GATE Mechanical Engineering (ME) 2012 Solved Paper

Show Para  Hide Para 
Question Numbers: 62-63
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
Activity Predecessors Duration (days)
Activity
Predecessors
Duration(days)
A
-
3
B
A
4
C
A
5
D
A
4
E
B
2
F
D
9
G
C, E
6
H
F, G
2