GATE Mechanical Engineering (ME) 2012 Solved Paper
Show Para
Question Numbers: 62-63
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
Activity Predecessors Duration (days)
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below.
Activity Predecessors Duration (days)
Activity |
Predecessors |
Duration(days) |
A |
- |
3 |
B |
A |
4 |
C |
A |
5 |
D |
A |
4 |
E |
B |
2 |
F |
D |
9 |
G |
C, E |
6 |
H |
F, G |
2 |