The process of planning for the next iteration should begin by analyzing the high-value user stories in the backlog. Also, the stories should be prioritized or reprioritized by the business partners. The other responses are incorrect.
Although they are included in the planning meeting, the analyzation of user stories in the backlog is performed first.