EVM looks to the future, trying to predict dates of completion and final costs, in addition to scope, schedule, and cost performance. The number of team members required and timings to begin new iterations are incorrect because they are
fluid dimensions and can’t easily be tracked. While the quality of deliverables can be tracked, they can’t be tracked in an EVM chart.