Unnecessary features is the correct answer. In addition, value can be maximized by eliminating partially done work, delays, extra processes, and features, task switching, waiting, moving information or a deliverable, defects, and handoffs.
Daily meetings, testing, and sprint reviews are incorrect because they represent just a few of the activities required for a successful project.